[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133319,796,1,"单选题","当承台底层土质为松软土，且能排干水施工时，承台底的正确处理方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按天然地基上修筑基础的施工方法进行施工",false,{"key":16,"text":17,"correct":18},"B","挖除松软土，换填10～30cm厚砂砾土垫层",true,{"key":20,"text":21,"correct":14},"C","用静水挖泥方法换填水稳性材料，立模灌注水下混凝土封底",{"key":23,"text":24,"correct":14},"D","在板桩围堰内填入砂砾至承台底面标高","本题考查的是桥梁承台施工。当承台底层土质有足够的承载力，又无地下水或能排干时，可按天然地基上修筑基础的施工方法进行施工。当承台底层土质为松软土，且能排干水施工时，可挖除松软土，换填10～30cm厚砂砾土垫层，如不能排干水时，用静水挖泥方法换填水稳性材料，立模灌筑水下混凝土封底后，再抽干水灌筑承台混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]