[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133315":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133315,796,1,"单选题","地下连续墙的施工工艺有： ①水下灌注混凝土；②导墙沟槽开挖； ③导墙施工；④槽底清理； ⑤拔接头管；⑥安放接头管； ⑦地连墙沟槽分段开挖； ⑧吊放钢筋笼，下列排序正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②①③⑥⑤⑦⑧④",false,{"key":16,"text":17,"correct":18},"B","②③⑦④⑥⑧①⑤",true,{"key":20,"text":21,"correct":14},"C","②③⑦④⑧⑥①⑤",{"key":23,"text":24,"correct":14},"D","⑦②①③④⑥⑦⑤","本题考查的是地下连续墙施工。地下连续墙的施工工艺为：导墙沟槽开挖→导墙施工→地连墙沟槽分段开挖→槽底清理→安放接头管→吊放钢筋笼→水下灌注混凝土→拔接头管。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]