[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133262":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133262,796,1,"单选题","试验段开工前28d安装好试验仪器和设备，配备好的试验人员报请（ ）审核。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理工程师",true,{"key":16,"text":17,"correct":18},"B","项目总工",false,{"key":20,"text":21,"correct":18},"C","项目经理",{"key":23,"text":24,"correct":18},"D","施工单位技术负责人","本题考查的是热拌沥青混凝土路面施工工艺及施工准备。试验段开工前28d安装好试验仪器和设备，配备好的试验人员报请监理工程师审核。参见教材P80。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]