[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133233,796,1,"单选题","对于水泥混凝土路面，符合设置纵向缩缝的情形是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","当一次铺筑宽度小于路面和硬路肩总宽度时",false,{"key":16,"text":17,"correct":18},"B","当一次铺筑宽度大于4.5m时",true,{"key":20,"text":21,"correct":14},"C","每天摊铺结束或摊铺中断时间超过30min时",{"key":23,"text":24,"correct":14},"D","当一次铺筑宽度大于4.0m时","本题考查的是水泥混凝土路面施工技术。当一次铺筑宽度大于4.5m时，应设置纵向缩缝，构造可采用设拉杆假缝型，锯切的槽口深度应大于纵向施工缝的槽口深度。参见教材P100。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]