[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133213,796,1,"单选题","下列沥青路面面层施工接缝处理的做法，错误的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","半幅施工不能采用热接缝时，采用人工顺直刨缝或切缝",false,{"key":16,"text":17,"correct":14},"B","半幅施工铺另半幅前必须将边缘清扫干净，并涂洒少量粘层沥青",{"key":19,"text":20,"correct":21},"C","横接缝首先用3m直尺检查端部平整度，不符合要求时，按45°斜交于路中线切齐清除",true,{"key":23,"text":24,"correct":14},"D","纵向冷接缝上、下层的缝错开15cm以上，横向接缝错开1m以上","主要考查沥青路面接缝施工。首先用3m直尺检查端部平整度。不符合要求时，垂直于路中线切齐清除。清理干净后在端部涂粘层沥青接着摊铺。摊铺时调整好预留高度，接缝处摊铺层施工结束后再用3m直尺检查平整度。横向接缝的碾压先用双轮双振压路机进行横压，碾压时压路机位于已压实的混合料层上伸人新铺层的宽为15cm，然后每压一遍向新铺混合料方向移动15-20cm，直至全部在新铺层上为止，再改为纵向碾压。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]