[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133203,796,1,"单选题","培土路肩的施工流程正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","备料→平整→静压→推平→切边→平整→碾压",false,{"key":16,"text":17,"correct":14},"B","备料→平整→静压→推平→碾压→切边→平整",{"key":19,"text":20,"correct":21},"C","备料→推平→平整→静压→切边→平整→碾压",true,{"key":23,"text":24,"correct":14},"D","备料→推平→静压→平整→碾压→平整→切边","",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]