[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133200":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133200,796,1,"单选题","无机结合料基层路拌法施工中关于接缝的处理，下列叙述中错误的是（）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","同日施工的两工作段衔接处应采用搭接",false,{"key":16,"text":17,"correct":14},"B","应该避免纵向接缝",{"key":19,"text":20,"correct":14},"C","纵缝必须垂直相接",{"key":22,"text":23,"correct":24},"D","纵缝可以垂直相接也可以斜接",true,"A；同日施工的两工作段衔接处应采用搭接，前一段拌合整形后，留5-8m不碾压，后一段施工时，前段留下未压部分，应再加部分水泥重新拌合，并与后一段一起碾压。D不应斜接。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]