[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133187,796,1,"单选题","填隙碎石底基层，拟采用干法施工，为使摊铺好的骨料稳定就位，初压时宜选用的压路机为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","两轮压路机",true,{"key":16,"text":17,"correct":18},"B","三轮压路机",false,{"key":20,"text":21,"correct":18},"C","羊足碾",{"key":23,"text":24,"correct":18},"D","胶轮压路机","本题考查的是路面粒料基层施工方法。初压用两轮压路机碾压3～4遍，使骨料稳定就位。参见教材P55。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]