[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133128":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133128,796,1,"单选题","土石路堤不能采用（ ）施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竖向填筑法",true,{"key":16,"text":17,"correct":18},"B","分层压实法",false,{"key":20,"text":21,"correct":18},"C","冲击压实法",{"key":23,"text":24,"correct":18},"D","强力夯实法","本题考查的是土石路堤、高填方路堤、粉煤灰路堤施工技术。土石路堤不得采用倾填方法（即竖向填筑法），只能采用分层填筑、分层压实。参见教材P12。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]