[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133113":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133113,796,1,"单选题","下列对于原地基处理要求的说法不正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基底原状土的强度不符合要求时，应进行换填",false,{"key":16,"text":17,"correct":14},"B","原地面的坑.洞.墓穴等应用合格填料回填",{"key":19,"text":20,"correct":21},"C","当路堤填土高度小于路床厚度时，路床压实度不宜小于基底压实度标准",true,{"key":23,"text":24,"correct":14},"D","路堤原地基横坡陡于1:5时，原地基应挖成台阶","本题考查的是原地基处理要求。基底应在填筑前进行压实。高速公路、一级公路、二级公路路堤基底的压实度应不小于90%，当路堤填土高度小于路床厚度时，基底的压实度不宜小于路床的压实度标准。参见教材P2。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]