[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133104":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133104,796,1,"单选题","山区公路中，雨期路基施工地段不宜选择（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","砂类土地段",false,{"key":16,"text":17,"correct":14},"B","路堑的弃方地段",{"key":19,"text":20,"correct":14},"C","碎砾石地段",{"key":22,"text":23,"correct":24},"D","重黏土地段",true,"（1）雨期路基施工地段一般应选择丘陵和山岭地区的砂类土、碎砾石和岩石地段和路堑的弃方地段。 （2）重黏土、膨胀土及盐渍土地段不宜在雨期施工;平原地区排水困难，不宜安排雨期施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]