[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133097":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133097,796,1,"单选题","袋装砂井处理软基的工艺流程中，“沉入砂袋”的前一道工序是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","打入套管",true,{"key":16,"text":17,"correct":18},"B","机具定位",false,{"key":20,"text":21,"correct":18},"C","埋砂袋头",{"key":23,"text":24,"correct":18},"D","摊铺下层砂垫层","袋装砂井按整平原地面→摊铺下层砂垫层→机具定位→打入套管→沉入砂袋→拔出套管→机具移位→埋砂袋头→摊铺上层砂垫层的施工工艺流程进行。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]