[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133078":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133078,796,1,"单选题","土质路堑开挖前应先施工的设施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","碎落台",false,{"key":16,"text":17,"correct":18},"B","截水沟",true,{"key":20,"text":21,"correct":14},"C","护坡道",{"key":23,"text":24,"correct":14},"D","边沟","本题考查的是路基雨期施工技术。土质路堑开挖前，在路堑边坡坡顶2m以外开挖截水沟并接通出水口。参见教材P14。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]