[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133070":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133070,796,1,"单选题","采用粒料桩处理软土地基时，其施工工艺程序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","整平地面→振冲器就位对中→成孔→清孔→加料振密→关机停水→振冲器移位",true,{"key":16,"text":17,"correct":18},"B","整平地面→振冲器移位→振冲器就位对中→成孔→清孔→加料振密→关机停水",false,{"key":20,"text":21,"correct":18},"C","整平地面→振冲器就位对中→振冲器移位→成孔→清孔→加料振密→关机停水",{"key":23,"text":24,"correct":18},"D","整平地面→振冲器就位对中→振冲器移位→成孔→加料振密→清孔→关机停水","本题考查的是软土地基处理施工技术。粒料桩处理软基的工艺：按整平地面→振冲器就位对中→成孔→清孔→加料振密→关机停水→振冲器移位的施工工艺程序进行。参见教材P22。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]