[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133064,796,1,"单选题","路基加高处理时，旧路槽恢复完之后必须整形，做成不小于（ ）%的双面横坡，然后再分层填筑，达到设计高程。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","本题考查的是路基加高施工技术要点。旧路槽恢复完之后必须整形，做成不小于4%的双向横坡，然后再分层填筑，达到设计高程。参见教材P16。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]