[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133059,796,1,"单选题","下列关于粒料桩采用振冲置换法施工规定的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在成孔过程中宜采用较大的水压和水量",false,{"key":16,"text":17,"correct":14},"B","成孔过程中振冲器的电流最大值不得超过额定电流值",{"key":19,"text":20,"correct":21},"C","当振冲器达到设计的加固深度后，宜立即将振冲器上提至孔口",true,{"key":23,"text":24,"correct":14},"D","密实电流尚未到达规定值，应提升振冲器加料","本题考查的是软土地基处理施工技术。选项C，正确的说法应为“当振冲器达到设计的加固深度后，宜停留1min，然后将振冲器上提至孔口，提升速度宜为5～6m\u002Fmin”。参见教材P21~22。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]