[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133047":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133047,796,1,"单选题","一般情况下，同一路段应先施工的路基地面排水设施是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","边沟",false,{"key":16,"text":17,"correct":14},"B","急流槽",{"key":19,"text":20,"correct":21},"C","截水沟",true,{"key":23,"text":24,"correct":14},"D","拦水带","本题考查的是边沟、截水沟和排水沟。一般情况下，同一路段应先施工的路基地面排水设施是截水沟。参见教材P38。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]