[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132992,796,1,"单选题","除厂家有规定外，（ ）kVA以上变压器应做器身检查。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","500",false,{"key":16,"text":17,"correct":14},"B","800",{"key":19,"text":20,"correct":21},"C","1000",true,{"key":23,"text":24,"correct":14},"D","1500","本题考查的是供配电及照明系统主要设施的施工技术要求。除厂家有规定外，1000kVA以上变压器应做器身检查。参见教材P280。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]