[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132958,796,1,"单选题","隧道涌水地段采用辅助坑道排水时，坑道应超前正洞（ ），至少应超过1～2个循环进尺。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5～10m",false,{"key":16,"text":17,"correct":14},"B","10～28m",{"key":19,"text":20,"correct":21},"C","10～20m",true,{"key":23,"text":24,"correct":14},"D","20～38m","本题考查的是涌水地段施工特点。采用辅助坑道排水时应符合的要求：（1）坑道应和正洞平行或接近平行；（2）坑道底标高应低于正洞底标高；（3）坑道应超前正洞10～20m，至少应超前1～2个循环进尺。参见教材P249。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]