[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132945,796,1,"单选题","二次衬砌的施作应在隧道位移相对值已达到相对位移量的（ ）以上后进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":14},"C","70%",{"key":22,"text":23,"correct":24},"D","90%",true,"本题考查的是隧道施工监控量测技术。二次衬砌的施作应在隧道位移相对值已达到相对位移量的90%以上后进行。参见教材P227。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]