[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132937":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132937,796,1,"单选题","隧道量测计划的编制依据不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隧道的围岩条件",false,{"key":16,"text":17,"correct":14},"B","支护类型和参数",{"key":19,"text":20,"correct":14},"C","施工方法以及所确定的量测目的",{"key":22,"text":23,"correct":24},"D","隧道的长度",true,"本题考查的是隧道施工监控量测技术。量测计划应根据隧道的围岩条件、支护类型和参数、施工方法以及所确定的量测目的进行编制。同时应考虑量测费用，并注意与施工的进程相适应。参见教材P225。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]