[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132930":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1132930,796,1,"单选题","公路隧道施工中仰拱以上的混凝土或片石混凝土应在仰拱混凝土达到设计强度的（ ）后施工。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70%",true,{"key":16,"text":17,"correct":18},"B","75%",false,{"key":20,"text":21,"correct":18},"C","80%",{"key":23,"text":24,"correct":18},"D","85%","本题考查的是模筑混凝土衬砌及公路隧道施工安全步距要求。仰拱以上的混凝土或片石混凝土应在仰拱混凝土达到设计强度的70%后施工。参见教材P238。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]