[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132895":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132895,796,1,"单选题","适用于各种地质条件的隧道地质超前预报方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","超前钻探法",false,{"key":16,"text":17,"correct":18},"B","地质调查法",true,{"key":20,"text":21,"correct":14},"C","物理勘探法",{"key":23,"text":24,"correct":14},"D","水力联系观测","本题考查的是隧道地质超前预报。地质调查法是隧道施工超前地质预报的基础，适用于各种地质条件隧道超前地质预报。",{"id":6,"name":27,"category":28,"favorite":29},"一建公路工程实务","建筑工程",0]