[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133935,795,1,"单选题","建设单位应自建设项目投入试生产之日起（ ）个月内，向有关部门申请该建设项目需要配套建设的环境保护设施竣工验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","2",{"key":23,"text":24,"correct":18},"D","5","2011年建设工程法规真题第44题 本题考查的是建设工程竣工环保验收。 根据《建设项目环境保护管理条例》的规定，环境保护设施竣工验收，应当与主体工程竣工验收同时进行。需要进行试生产的建设项目，建设单位应当自建设项目投入试生产之日起3个月内，向审批该建设项目环境影响报告书、环境影响报告表或者环境影响登记表的环境保护行政主管部门，申请该建设项目需要配套建设的环境保护设施竣工验收。 综上所述，本题的正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]