[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133933,795,1,"单选题","建设单位应当在（ ）向规划部门提出规划验收申请。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","竣工验收前",false,{"key":16,"text":17,"correct":14},"B","竣工验收同时",{"key":19,"text":20,"correct":21},"C","竣工验收后6个月内",true,{"key":23,"text":24,"correct":14},"D","竣工验收后1个月内","根据《城乡规划法》的规定，县级以上地方人民政府城乡规划主管部门按照国务院规定对建设工程是否符合规划条件予以核实。未经核实或者经核实不符合规划条件的，建设单位不得组织竣工验收。建设单位应当在竣工验收后六个月内向城乡规划主管部门报送有关竣工验收资料。 综上所述，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]