[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133914":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1133914,795,1,"单选题","工程经建设单位组织验收合格后投入使用，2年后外墙出现裂缝，经查是由于设计缺陷造成的，则下列说法正确的是（ ）。2014",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位维修，建设单位直接承担费用",true,{"key":16,"text":17,"correct":18},"B","建设单位维修并承担费用",false,{"key":20,"text":21,"correct":18},"C","施工单位维修并承担费用",{"key":23,"text":24,"correct":18},"D","施工单位维修，设计单位直接承担费用","本题考查的是竣工工程质量争议的处理。建设工程竣工时发现的质量问题或者质量缺陷，无论是建设单位的责任还是施工单位的责任，施工单位都有义务进行修复或返修。但是，对于非施工单位原因出现的质量问题或质量缺陷，其返修的费用和造成的损失是应由责任方承担的。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]