[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133894":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133894,795,1,"单选题","某施工合同约定以《建设工程价款结算暂行办法》作为结算依据，该工程结算价约4000万元，发包人应从接到承包人竣工结算报告和完整的竣工结算资料之日起（ ）天内核对（审查）完毕并提出审查意见。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":14},"C","60",{"key":22,"text":23,"correct":24},"D","45",true,"2011年建设工程法规真题第58题 本题考查的是工程竣工结算。 根据《建设工程价款结算暂行办法》第14条的规定，单项工程竣工后，承包人应在提交竣工验收报告的同时，向发包人递交竣工结算报告及完整的结算资料，工程竣工结算金额为2000万元以上、5000万元以下的，发包人应从接到承包人竣工结算资料之日起45天内核对（审查）完毕并提出审查意见。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]