[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133892":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1133892,795,1,"单选题","按照《建设工程价款结算暂行办法》的规定，发包人收到竣工结算报告及完整的结算资料后，在规定的时间或合同约定期限内，对结算报告及资料没有提出意见，则视同（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拒绝",false,{"key":16,"text":17,"correct":14},"B","协商",{"key":19,"text":20,"correct":21},"C","认可",true,{"key":23,"text":24,"correct":14},"D","应予造价鉴定","根据《建设工程价款结算暂行办法》第16条第1款的规定，发包人收到竣工结算报告及完整的结算资料后，在本办法规定或合同约定期限内，对结算报告及资料没有提出意见，则视同认可。 综上所述，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]