[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1133762,795,1,"单选题","按照《建设工程施工合同文本》通用条款规定，工程具备隐蔽条件后，施工单位进行自检，并在隐蔽前（ ）以书面形式通知监理工程师验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1日",false,{"key":16,"text":17,"correct":14},"B","36小时",{"key":19,"text":20,"correct":14},"C","24小时",{"key":22,"text":23,"correct":24},"D","48小时",true,"根据《建设工程施工合同文本》的规定，工程具备隐蔽条件或达到专用条款约定的中间验收部位，施工单位进行自检，并在隐蔽或者中间验收前48小时以书面形式通知监理工程师验收。验收不合格的，施工单位在监理工程师限定的时间内修改并重新验收。如果工程质量符合标准规范和设计图纸等要求，验收24小时后，监理工程师不在验收记录上签字的，视为已经批准，施工单位可继续进行隐蔽或施工。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]