[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133735":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1133735,795,2,"多选题","某工程建设施工方拟采用某种新材料，但这种新材料不符合现行强制性标准规定，则（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该新材料不得采用",false,{"key":16,"text":17,"correct":18},"B","提请建设单位组织专题技术论证",true,{"key":20,"text":21,"correct":14},"C","施工方组织专题技术论证",{"key":23,"text":24,"correct":18},"D","报批准标准的建设行政主管部门审定",{"key":26,"text":27,"correct":14},"E","报批准标准的建设行政主管部门备案","BD","根据《实施工程建设强制性标准监督规定》的规定，工程建设中拟采用的新技术、新工艺、新材料，不符合现行强制性标准规定的，应当由拟采用单位提请建设单位组织专题技术论证，报批准标准的建设行政主管部门或者国务院有关主管部门审定。 综上所述，本题的正确答案为BD。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]