[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133689":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1133689,795,2,"多选题","施工企业保证工程质量的最基本要求包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","不得压缩合同工期",false,{"key":16,"text":17,"correct":18},"B","按设计图纸施工",true,{"key":20,"text":21,"correct":14},"C","与监理单位建立友好的沟通关系",{"key":23,"text":24,"correct":14},"D","严格履行企业质量管理认证体系",{"key":26,"text":27,"correct":18},"E","不擅自修改设计文件","BE","2012年建设工程法规真题第71题 本题主要考查按照工程设计图纸和施工技术标准施工的规定。 《建设工程质量管理条例》规定，施工单位必须按照工程设计图纸和施工技术标准施工，不得擅自修改工程设计，不得偷工减料。施工单位在施工过程中发现设计文件和图纸有差错的，应当及时提出意见和建议。 按图施工、不得擅自修改设计，是施工单位保证工程质量的最基本要求。 综上所述，本题正确答案为BE。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]