[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1133685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1133685,795,1,"单选题","甲施工单位于2013年5月20日签订施工合同，承建工程为5层砖混结构，7级抗震设防，施工图通过审批。工程于2013年10月8日开工建设，施工中技术人员发现图纸有一处抗震设计差错，此时甲施工企业应当（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按原图纸继续施工",false,{"key":16,"text":17,"correct":18},"B","及时提出意见和建议",true,{"key":20,"text":21,"correct":14},"C","与监理工程师协商一致后，继续施工",{"key":23,"text":24,"correct":14},"D","自行修正后继续施工，向建设单位提出增加费用","如果施工单位在施工过程中发现设计文件和图纸中确实存在差错，有义务及时向设计单位提出，避免造成不必要的损失和质量问题。这是施工单位应具备的职业道德，也是履行合同应尽的基本义务。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]