[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132683,795,1,"单选题","（2019年真题）建设项目完工后，施工企业已提交竣工验收报告，如建设单位未组织竣工验收，当事人对建设工程实际竣工日期有争议的，该项目的竣工日期（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","相应顺延",false,{"key":16,"text":17,"correct":18},"B","以施工企业提交竣工验收报告之日为准",true,{"key":20,"text":21,"correct":14},"C","以合同约定的计划竣工日期为准",{"key":23,"text":24,"correct":14},"D","以实际通过竣工验收之日为准","P130-135 当事人对建设工程实际竣工日期有争议的，按照以下情形分别处理: (1)建设工程经竣工验收合格的，以竣工验收合格之日为竣工日期； (2)承包人已经提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期； (3)建设工程未经竣工验收，发包人擅自使用的，以转移占有建设工程之日为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]