[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132676,795,1,"单选题","承包人已经提交竣工验收报告，发包人拖延验收的，竣工日期（ ）。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以合同约定的竣工日期为准",false,{"key":16,"text":17,"correct":14},"B","相应顺延",{"key":19,"text":20,"correct":21},"C","以承包人提交竣工报告之日为准",true,{"key":23,"text":24,"correct":14},"D","以实际通过的竣工验收之日为准","本题考查的是建设工程工期。承包人已经提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]