[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132663":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132663,795,1,"单选题","施工中发包人如需提前竣工，以下做法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人只需要提前书面通知承包人提前竣工的时间",false,{"key":16,"text":17,"correct":14},"B","发包人需要通知通知承包人提前竣工的时间及追加的价款",{"key":19,"text":20,"correct":21},"C","发包人需要与承包人协商一致，签订提前竣工协议",true,{"key":23,"text":24,"correct":14},"D","发包人与承包人需要针对此工程另订协议","根据《建设工程施工合同（示范文本）》的规定，施工中发包人如需提前竣工，双方协商一致后应签订提前竣工协议，作为合同文件组成部分。提前竣工协议应包括承包人为保证工程质量和安全采取的措施、发包人为提前竣工提供的条件以及提前竣工所需的追加合同价款等内容。 综上所述，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]