[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132657,795,1,"单选题","建设工程施工合同签订后，发包人合同外附属市政工程委托承包人施工，对此价款未做约定，后无法协商一致，则市政工程价款应按照（ ）市场价格履行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","订立合同时合同签订地",false,{"key":16,"text":17,"correct":18},"B","订立合同时合同履行地",true,{"key":20,"text":21,"correct":14},"C","履行合同时合同签订地",{"key":23,"text":24,"correct":14},"D","履行合同时合同履行地","《合同法》规定，合同生效后，当事人就质量、价款或者报酬、履行地点等内容没有约定或者约定不明确的，可以协议补充；不能达成补充协议的，按照合同有关条款或者交易习惯确定。 按照以上方法仍无法确定的，价款或者报酬不明确的，按照订立合同时履行地的市场价格履行；依法应当执行政府定价或者政府指导价的，按照规定履行。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]