[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1132651,795,1,"单选题","承包人、发包人以《建设工程施工合同（示范文本）》签订合同，在施工中，发包人申请延期开工，应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","书面通知承包人，并顺延工期",true,{"key":16,"text":17,"correct":18},"B","承包人应在48小时内予以确认",false,{"key":20,"text":21,"correct":18},"C","承包人不予确认的工期不得顺延",{"key":23,"text":24,"correct":18},"D","征得承包人同意后顺延工期","根据《建设工程施工合同（示范文本）》的规定，因发包人原因不能按照协议书约定的开工日期开工，工程师应以书面形式通知承包人，推迟开工日期。发包人赔偿承包人因延期开工造成的损失，并相应顺延工期。 综上所述，本题的正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]