[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132635":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1132635,795,2,"多选题","关于工程竣工验收的说法，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程竣工验收合格的，以承包人送交竣工验收报告之日为竣工日期",true,{"key":16,"text":17,"correct":14},"B","承包人送交竣工验收报告后，当事人对工程质量发生争议，工程质量经鉴定合格的，以承包人送交竣工验收报告之日为竣工日期",{"key":19,"text":20,"correct":21},"C","工程按发包人要求修改后经竣工验收合格的，以承包人首次送交竣工验收报告之日为竣工日期",false,{"key":23,"text":24,"correct":14},"D","承包人送交竣工验收报告后，发包人拖延验收的，以承包人送交竣工验收报告之日为竣工日期",{"key":26,"text":27,"correct":14},"E","建设工程未经验收，发包人擅自使用的，以建设工程转移占有之日为竣工日期","ABDE","@jin",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]