[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132603,795,1,"单选题","某施工合同约定质量标准为合格，监理工程师在巡视时要求承包人“把活儿做得更细些，到时不会少了你们的”。于是项目经理在施工中提高了质量标准，因此增加了费用，则该笔费用应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理工程师",{"key":23,"text":24,"correct":14},"D","承包人与发包人共同","2007年建设工程法规真题第43题 合同变更应当经合同双方协商一致。如果一方当事人未经对方同意就改变合同的内容，对另一方当事人没有约束力。 监理单位不属于合同的当事人，因此施工方面单方面变更的，费用自行承担。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]