[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132502,795,1,"单选题","某施工项目材料采购合同中，双方约定的违约金为4万元、定金为6万元。采购方依约支付了6万元定金，供货方违约后，采购方有权主张的最高给付金额为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","16",false,{"key":16,"text":17,"correct":14},"B","10",{"key":19,"text":20,"correct":21},"C","12",true,{"key":23,"text":24,"correct":14},"D","4","2010年建设工程法规真题第16题 本题主要考查承担违约责任的种类。 根据《合同法》的规定，给付定金的一方不履行约定的债务的，无权要求返还定金；收受定金的一方不履行约定的债务的，应当双倍返还定金。 本题中，采购方支付了定金后，供货方违约，因此应当返还双倍定金，即6×2=12万元。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]