[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132490,795,1,"单选题","水泥厂为承包商供应水泥，承包商已经支付了全部货款。交货时承包商因水泥厂交货时间经合同约定晚了两天而要求支付违约金，水泥厂表示拒绝并把水泥卸放在合同约定的地点。第二天上午乌云密布，下午降暴雨把部分水泥淋湿硬化。则该部分损失（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","由水泥厂承担",false,{"key":16,"text":17,"correct":18},"B","由承包商承担",true,{"key":20,"text":21,"correct":14},"C","由水泥厂和承包商共同承担",{"key":23,"text":24,"correct":14},"D","由承包商向水泥厂索赔","2006年建设工程法规真题第44题 《合同法》规定，当事人一方违约后，对方应当采取适当措施防止损失的扩大；没有采取适当措施致使损失扩大的，不得就扩大的损失要求赔偿。 本题中，水泥厂违约延期交货后，承包商应当采取相应的措施保护水泥，防止损失扩大；承包商没有采取适当的措施，致使水泥被雨淋硬化，损失应由承包商自行承担，不得要求水泥厂赔偿。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]