[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132484":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1132484,795,2,"多选题","继续实际履行合同作为承担违约责任的方式之一，其构成要件包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","必须有违约行为存在",true,{"key":16,"text":17,"correct":14},"B","必须由守约方在合理期限内提出继续履行合同要求",{"key":19,"text":20,"correct":14},"C","继续实际履行须在事实上可能",{"key":22,"text":23,"correct":24},"D","继续实际履行仅限于价款和报酬的给付",false,{"key":26,"text":27,"correct":14},"E","必须依据法律和合同的性质能够履行","ABCE","2006年建设工程法规真题第90题 继续履行的构成要件包括：（1）存在违约行为；（2）须有守约方请求违约方继续履行合同债务的行为；（3）须违约方能够继续履行，不论事实上还是法律上都存在存在履行的可能。 综上所述，本题正确答案为ABCE。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]