[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132482,795,1,"单选题","甲建设单位与乙设计院签订设计合同，设计费用为300万元，双方在协商定金数额时发生意见分歧。根据《担保法》的规定，该定金数额最多为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","45",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","90","2006年建设工程法规真题第51题 定金数额不得超过主合同标的额的20%。 本题中设计费为300万元，因此定金最多为300×20%=60万元。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]