[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132470,795,1,"单选题","甲施工企业与乙水泥厂签订水泥供应合同，在约定的履行日期届满时，水泥厂未能按时供应水泥。由于甲施工企业没有采取适当措施寻找货源，致使损失扩大。对于扩大的损失应 该由（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","乙水泥厂承担",false,{"key":16,"text":17,"correct":14},"B","双方连带责任",{"key":19,"text":20,"correct":14},"C","双方按比例承担",{"key":22,"text":23,"correct":24},"D","甲施工企业承担",true,"本题考查的是赔偿损失的限制。《合同法》规定，当事人一方违约后，对方应当采取适当措施防止损失的扩大；没有采取适当措施致使损失扩大的，不得就扩大的损失要求赔偿。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]