[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132469":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1132469,795,1,"单选题","某工程施工中某水泥厂为施工企业供应水泥，延迟交货一周，延迟交货导致施工企业每天损失0.4万元，第一天晚上施工企业为减少损失，采取紧急措施共花费1万元，使剩余6天共损失0.7万元。2018真题则水泥厂因违约应向施工企业赔偿的损失为（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.1万元",false,{"key":16,"text":17,"correct":14},"B","1.7万元",{"key":19,"text":20,"correct":21},"C","2.1万元",true,{"key":23,"text":24,"correct":14},"D","2.8万元","本题考查的是建设工程赔偿损失的规定。《合同法》规定，当事人一方违约后，对方应当采取适当措施防止损失的扩大；没有采取适当措施致使损失扩大的，不得就扩大的损失要求赔偿。当事人因防止损失扩大而支出的合理费用，由违约方承担。故水泥厂因违约应向施工企业赔偿的损失为0.4+1+0.7=2.1（万元）。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]