[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132439":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1132439,795,1,"单选题","某施工企业向某材料供应商发出了要约，材料供应商在对施工企业的答复中仅仅要求将交货时间推迟一天。根据《合同法》的规定，材料供应商的答复是对施工企业要约的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实质性变更，该承诺有效",false,{"key":16,"text":17,"correct":18},"B","实质性变更，不构成承诺",true,{"key":20,"text":21,"correct":14},"C","非实质性变更，不构成承诺",{"key":23,"text":24,"correct":14},"D","非实质性变更，视为新要约","《合同法》规定，承诺的内容应当与要约的内容一致。受要约人对要约的内容作出实质性变更的，为新要约。有关合同标的、数量、质量、价款或者报酬、履行期限、履行地点和方式、违约责任和解决争议方法等的变更，是对要约内容的实质性变更。 本题中，材料供应商在对施工企业的答复中仅仅要求将交货时间推迟一天，属于履行期限的变更，属于实质性变更，不构成承诺，而是属于新要约。 综上所述，本题正确答案为B",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]