[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132139":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1132139,795,2,"多选题","注册建造师不得同时承担两个及以上建设工程施工的项目经理，但下列选项中的（ ）情况除外。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","同一工程相邻分段发包或分期施工的",true,{"key":16,"text":17,"correct":14},"B","因非承包方原因使工程停工120天以上且建设单位同意的",{"key":19,"text":20,"correct":21},"C","合同约定的工程进入收尾阶段而新的工程刚刚破土动工的",false,{"key":23,"text":24,"correct":21},"D","因工作需要经工程发、承包双方协商同意的",{"key":26,"text":27,"correct":14},"E","合同约定的工程验收合格","ABE","根据《注册建造师执业管理办法（试行）》的规定，注册建造师不得同时担任两个及以上建设工程施工项目负责人。发生下列情形之一的除外：（一）同一工程相邻分段发包或分期施工的；（二）合同约定的工程验收合格的；（三）因非承包方原因致使工程项目停工超过120天（含），经建设单位同意的。 A项属于（一）；B项属于（三）；E项属于（二）；CD项则不符合上述规定。 综上所述，本题的正确答案为ABE。",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]