[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132062":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1132062,795,2,"多选题","关于施工许可制度和形式报告制度的说法，正确的有（ ）。 2016",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","实行形式报告批准制度的工程，必须符合国务院的有关规定",true,{"key":16,"text":17,"correct":14},"B","建设单位领取施工许可证后因故不能近期开工的，最多可延期6个月",{"key":19,"text":20,"correct":14},"C","建设工程因故中止施工满一年的，恢复施工前应报发证机关核验施工许可证",{"key":22,"text":23,"correct":14},"D","实行开工报告批准制度的工程，因故不能近期开工超过6个月的工程，应当重新办理开工报告审批手续",{"key":25,"text":26,"correct":27},"E","实行形式报告批准制度的工程，其开工报告主要反映的是施工企业应具备的开工条件",false,"ABCD","本题考查的是延期开工、核验和重新办理批准的规定。选项E，实 行形式报告批准制度的工程，其开工报告主要反映的是建设单位应具备的开工条件。 @jin",{"id":6,"name":31,"category":32,"favorite":33},"一建工程法规及相关知识","建筑工程",0]