[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132058":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132058,795,1,"单选题","某剧院工程，建设单位在领取施工许可证后满一年才开工，则开工时（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位应当向发证机关报告",false,{"key":16,"text":17,"correct":14},"B","应当报发证机关核验施工许可证",{"key":19,"text":20,"correct":14},"C","应当报发证机关申请延期",{"key":22,"text":23,"correct":24},"D","施工许可证已自行作废",true,"根据《建筑法》第九条的规定，建设单位应当自领取施工许可证之日起三个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过三个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。 本题中，建设单位在领取施工许可证一年后才开工，期间未申请延期且不开工超过三个月，因此，施工许可证依据上述规定已经自行废止。 综上所述，本题的正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]