[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1132049":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1132049,795,1,"单选题","建设单位因故不能按期开工的，应当向（ ）申请延期。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","上级主管",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","发证机关",true,"2005年建设工程法规真题第49题 根据《中华人民共和国建筑法》的规定，建设单位应当自领取施工许可证之日起三个月内开工。因故不能按期开工的，应当向发证机关申请延期；延期以两次为限，每次不超过三个月。既不开工又不申请延期或者超过延期时限的，施工许可证自行废止。 综上所述，本题正确答案是D。",{"id":6,"name":27,"category":28,"favorite":29},"一建工程法规及相关知识","建筑工程",0]